Skip to content

A Lien On Your House

MCL 570.1111 — a claim of lien within 90 days, and a year to foreclose

In Michigan, a contractor, subcontractor, laborer or supplier who improves real property has a right to a construction lien under the Construction Lien Act, and that right ends unless the claim of lien is recorded in time.

Email
The stepThe statute's answer
The stepNotice of furnishing, from a subcontractor or supplierThe statute's answerWithin 20 days after first furnishing labor or material, to the designee and general contractor named in the notice of commencement; a contractor who contracted directly with the owner needs none
The stepRecording the claim of lienThe statute's answerWithin 90 days after the claimant's last furnishing, with the register of deeds in each county where the property is
The stepSuing to enforce itThe statute's answerNot later than 1 year after the claim of lien was recorded

The sworn statement. A contractor or subcontractor suing to foreclose must show the owner was provided a sworn statement, if one was requested or required.

The notice of commencement and the protection the act gives an owner who paid the contractor are in sections not on this page. Whether a particular lien is valid, and how to contest or discharge one, are questions for a licensed Michigan attorney.

Sources for this section (3)
  1. MCL 570.1111 — Claim of lien; recording; validity; form
  2. MCL 570.1109 — Notice of furnishing by subcontractor, supplier or laborer
  3. MCL 570.1117 — Action for enforcement of construction lien through foreclosure

Legal information, not legal advice. Verified as of September 2026. Applying it to a particular situation is the work of a licensed Michigan attorney.

From here