A Lien On Your House

RCW 60.04.091 — a claim of lien within ninety days, and eight months to sue

In Washington, a person furnishing professional services, materials or equipment gives the owner written notice of the right to claim a lien. It protects only what was supplied after a date sixty days before the notice, or ten days before it on new construction of a single-family residence.

Email
The stepThe statute's answer
The stepRecording the claim of lienThe statute's answerNot later than ninety days after the claimant stops furnishing labor, services, materials or equipment, in the county where the property is
The stepHow long it bindsThe statute's answerEight calendar months after recording, unless an action is filed in that time and served on the owner within ninety days of filing

Whether a particular lien is valid, and how to contest or discharge one, are questions for a licensed Washington attorney.

Sources for this section (3)
  1. RCW 60.04.091 — Recording; time; contents of lien
  2. RCW 60.04.031 — Notices; exceptions
  3. RCW 60.04.141 — Lien; duration; procedural limitations

Legal information, not legal advice. Verified as of September 2026. Applying it to a particular situation is the work of a licensed Washington attorney.