Neb. Rev. Stat. § 52-137 and Neb. Rev. Stat. § 52-140 — recorded within one hundred twenty days, and enforceable for two years

One hundred twenty days. A contractor's or supplier's lien does not attach and cannot be enforced unless it is recorded no later than one hundred twenty days after the claimant's final furnishing of services or materials.

  • Neb. Rev. Stat. § 52-137
Email

A recorded lien stays enforceable for two years after recording.

  • Neb. Rev. Stat. § 52-140

A demand to sue. An owner may give the claimant a written demand to start a court proceeding, and the lien lapses unless within thirty days the claimant sues or records an affidavit that the contract price is not yet due.

  • Neb. Rev. Stat. § 52-140

Priority among liens is set out in the chapter. A particular lien is a question for a licensed Nebraska attorney.

  • Neb. Rev. Stat. § 52-140
Sources for this section (2)
  1. Neb. Rev. Stat. § 52-137 — Attachment and enforcement of lien; recording required; time limitation; attachment, when
  2. Neb. Rev. Stat. § 52-140 — Duration of lien; demand to institute judicial proceedings; continuation of lien during pendency of proceeding

Legal information, not legal advice. Verified as of October 2026. Applying it to a particular situation is the work of a licensed Nebraska attorney.